40 MWe waste-to-energy, Belgrade, and Songkhla waste-to-energy, Thailand

One partner across two continents: independent FAT witnessing for the Belgrade waste-to-energy plant in 2020, and the Songkhla plant in southern Thailand in 2026 — ten years of collaboration with CNIM Martin, now Martin Technology Private Limited.

Martin Technology (formerly CNIM Martin) · Belgrade, Serbia · Songkhla, Thailand · 2020 – present

Factory acceptance test of the 40 MWe alternator for the Belgrade waste-to-energy plant
Factory acceptance test of the 40 MWe alternator for the Belgrade waste-to-energy plant.

What we did

Third-party quality testing — factory acceptance test witnessing of the 40 MWe Belgrade alternator (2020) · on site at the Songkhla waste-to-energy plant, Thailand (2026).

One partner, one name change

Martin Technology Private Limited is the current name of CNIM Martin Private Limited. The company changed its name; the relationship did not. Belgrade in 2020 and Songkhla in 2026 are not two unrelated jobs for two different clients — they are two points on the same line, and the work in Thailand continues the work that started in Serbia.

Belgrade, 2020 — witnessing the 40 MWe alternator

The Vinča plant outside Belgrade is one of Europe’s largest waste-to-energy projects: 103 MW of heat and electricity, delivered as a public–private partnership by the Beo Čista Energija consortium led by SUEZ with the European fund Marguerite.

REURASIA was tasked with supporting the Generator Factory Acceptance Test on the steam turbine generator at the WEG factory in Tamil Nadu, India — and with assessing the most realistic delivery date for the machine, a judgement CMPL, Tractebel and SUEZ relied on. Third-party quality work of that kind only goes to engineers a manufacturer’s client trusts.

Songkhla, 2026 — on site in Thailand

Six years later the same partner is at work in southern Thailand, and REURASIA is with them at the Songkhla waste-to-energy plant, photographed in July 2026.

Why it matters

A technology provider does not bring the same engineers back after six years out of politeness. Belgrade was a test of judgement against a delivery deadline; Songkhla is what passing it earns. When you are choosing who checks your equipment, the useful question is not who has done it once — it is who has been asked again.

Sector: Developers and technology providers. All references: the reference list.

Songkhla, Thailand — July 2026

Our own photographs of the plant, taken on site.

Stack and boiler hall of the Songkhla waste-to-energy plant, Thailand
The stack and the boiler hall.
The Songkhla waste-to-energy plant seen from the site perimeter
The plant from the site perimeter.
Exterior of the Songkhla waste-to-energy plant, Thailand
Plant exterior.
Exterior view of the Songkhla waste-to-energy plant buildings
The plant buildings.
Pipe rack and site gate at the Songkhla waste-to-energy plant
Pipe rack and site gate.
The control building at the Songkhla waste-to-energy plant
The control building.
Pipe rack running through the Songkhla waste-to-energy plant
Pipe rack running through the site.
Site road at the Songkhla waste-to-energy plant, Thailand
The site road.

Tell us about your site